TERMS OF REFERENCE

SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF AUTOMATIC IRRIGATION SYSTEM FOR SIX TENNIS COURTS

IRRIGATION WORKS

FÉDÉRATION RWANDAISE DE TENNIS

Kigali, Rwanda

1.Introduction
 

FEDERATION RWANDAISE DE TENNIS(FRT) intends to improve the playing conditions and usability of the tennis courts at IPRC-Kicukiro through the installation of an automatic irrigation system serving six (6) tennis courts. The works shall be undertaken in accordance with the requirements set out in these Terms of Reference and the accompanying Bills of Quantities (BOQs).

The Contractor shall be responsible for the supply, installation, testing, commissioning and handover of the specified system, including all necessary accessories, connections, civil works, labour, tools and equipment required for a complete and operational installation.

2. Selection Criteria

Interested bidders shall submit a technical proposal demonstrating their understanding of the assignment and their capacity to supply and install the automatic irrigation system. The proposal shall be technically compliant with the specifications and quantities in the BOQ.

The proposed solution shall be reliable, safe, suitable for the intended tennis court use and economically viable. Bidders shall inspect the site and take account of the existing conditions, available water storage facilities and routing of pipes.

3. Submittals

  • Company profile and valid business registration documents.
  • Valid tax clearance and VAT registration certificate, as applicable.
  • Evidence of experience in the supply and installation of irrigation systems or comparable mechanical installations, supported by completion certificates or client references.
  • Technical proposal describing the proposed execution methodology for the automatic irrigation system serving six (6) tennis courts.
  • Technical datasheets and manufacturer information for the proposed sprinklers, valves, irrigation controller, pump, pipes, fittings and other major equipment.
  • Proposed layout drawings showing sprinkler positions, pipe routes, valve locations and pump arrangement, for approval before installation.
  • Priced Bill of Quantities showing unit rates, quantities and total cost, with applicable taxes clearly indicated.
  • Project implementation schedule, including procurement, delivery, installation, testing and commissioning activities.
  • Quality assurance, occupational health and safety, and environmental protection measures.
  • List of proposed key technical personnel, with CVs, qualifications and relevant experience.
  • Manufacturer or supplier authorization, where applicable, and warranty information for the supplied equipment.
  • Evidence of financial and logistical capacity to execute and complete the assignment.

4. Key Technical Staff

The bidder shall propose qualified and experienced personnel appropriate to the nature and scale of the works. The proposed team shall include, at a minimum:

  • Project Manager: responsible for overall coordination, program, quality and delivery of the assignment.
  • Irrigation Specialist/Engineer: experienced in the design, installation and commissioning of automatic irrigation systems, pumps, valves, controllers and HDPE pipe networks.
  • Plumber/Pipe Installation Technician: experienced in pipe network installation, fittings, valves and pressure testing.

Bidders shall provide CVs and copies of relevant academic/professional qualifications and evidence of experience for the proposed personnel.

5. Project Objectives

  • Provide an automatic irrigation system capable of distributing water to all six (6) tennis courts.
  • Provide adequate and reasonably uniform sprinkler coverage across the intended court areas.
  • Improve the reliability, operational efficiency and usability of the tennis court facilities.
  • Ensure that the installed system is safe, maintainable and supported by appropriate operating instructions and warranties.

6. Scope of Works of Successful Bidder

6.1. General requirements

  • Visit and verify the site conditions, dimensions, access routes, existing water storage arrangements and routing of pipes before commencing the works.
  • Prepare and submit detailed installation drawings and equipment data for the Employer’s review and approval.
  • Supply all materials, equipment, accessories, labour, tools, transport and installation services required for a complete and functional system.
  • Coordinate the works with the Employer and the facility management team to minimize disruption to the use of the courts.
  • Protect existing facilities and reinstate any surfaces or areas disturbed during the works.

6.2. Automatic irrigation system for six (6) tennis courts

The Contractor shall supply and install an automatic irrigation system in accordance with the irrigation BOQ. The specified principal components include:

  • Pop-up rotor sprinklers, 3/4-inch, Hunter or Rain Bird or approved equivalent, with a stated radius of 12 m; 10 units per court.
  • Solenoid valves, 1½-inch; 4 units per court, together with professional circular valve boxes.
  • Rain Bird model or approved equivalent irrigation controller with 8 stations.
  • HDPE main line pipe, PN10, 50 mm, and HDPE lateral pipes, PN6, 32 mm, including the specified pipe lengths and fittings.
  • Flexible swing-joint connections, HDPE fittings and multi-core irrigation control cabling of 2.5 mm².
  • Multistage centrifugal or submersible booster pump set with a stated capacity of 7.2 m³/hour and power rating of 1.5 hp, including electrical and control components.
  • Connection to the existing/client-provided water storage tanks. The BOQ identifies the water storage tanks as existing/provided by the client.

The Contractor shall install, connect and configure the system so that the irrigation zones operate through the controller and solenoid valves. The Contractor shall verify water pressure and flow, check for leakage, adjust sprinkler coverage and demonstrate the operation of each zone.

6.3. Testing and commissioning

  • Carry out pressure and leakage tests on the irrigation pipe network and verify the operation of sprinklers, solenoid valves, controller and pump.
  • Verify water pressure and flow, adjust sprinkler coverage and demonstrate the operation of each irrigation zone.
  • Rectify defects identified during inspection, testing and commissioning at no additional cost to the Employer.

7. Handover

  • Submit operation and maintenance manuals for the irrigation system.
  • Provide equipment datasheets, irrigation layout and as-built drawings, controller/programming details, test certificates and warranty certificates.
  • Provide practical training to the Employer’s designated facility operation and maintenance staff.
  • Demonstrate the complete operation of the system and hand over all keys, accessories and control settings.

8. Performance Requirements

  • The automatic irrigation system shall serve all six (6) tennis courts and operate through the specified controller, valves, pump and sprinkler network.
  • The irrigation system shall provide adequate and reasonably uniform sprinkler coverage across the intended court areas, without material leakage from the installed network.
  • The pumping system shall meet the capacity of 7.2 m³/hour and 1.5 hp, subject to verification against the actual site conditions.
  • The system shall be fully operational, safe and maintainable at the time of handover.

9. Quality Standards

  • All materials and equipment shall be new, unused and from reputable manufacturers.
  • Equipment shall comply with the specifications in the BOQ and relevant applicable IEC, ISO or equivalent standards.
  • Workmanship shall be of good professional quality and comply with applicable national construction and occupational safety requirements.

10. Program and Timeline

Bidders shall submit a realistic implementation schedule covering site verification, submission of drawings, procurement and delivery of materials, civil works, installation, testing, commissioning and handover. The proposed schedule shall clearly indicate the duration and sequence of each activity. The final implementation period shall be agreed with the Employer and stated in the contract.

11. Deliverables

  • Approved irrigation layout/shop drawings and technical datasheets.
  • Complete automatic irrigation system installed and operational for six (6) tennis courts.
  • Completed pipe network, fittings, valves, valve boxes, pump installation, connections and reinstatement.
  • Testing and commissioning reports for the irrigation installation.
  • As-built drawings, operation and maintenance manuals, warranties and equipment documentation.
  • Training of designated facility operation and maintenance staff.
  • Final completion and handover report.

12. Contractor Obligations

  • Provide qualified personnel, adequate tools, equipment and supervision to complete the works.
  • Supply materials and equipment in accordance with the approved technical specifications and BOQ.
  • Ensure proper storage, handling and protection of materials and existing facilities.
  • Comply with applicable environmental, occupational health and safety requirements and provide appropriate personal protective equipment.
  • Maintain site records and submit progress reports as required by the Employer.
  • Obtain approval before making any changes to the approved materials, layout or installation arrangements.
  • Correct defects arising during installation, testing and the applicable defects liability period.
  • Provide warranties for supplied equipment and workmanship. The proposed warranty/defects liability period shall be clearly stated in the bid.

13. Employer’s Obligations

  • Provide access to the IPRC-Kicukiro site and facilitate coordination with the facility management team.
  • Make available the existing/client-provided water storage tanks identified in the irrigation BOQ.
  • Provide available information on existing water connection points, where applicable.
  • Review submitted drawings, technical information and work plans within a reasonable period.
  • Facilitate inspection and acceptance of completed works and process payments in accordance with the contract.

14. Governance and Oversight

  • FEDERATION RWANDAISE DE TENNIS(FRT) or its designated representative shall oversee implementation of the assignment.
  • The Contractor shall coordinate regularly with the Employer and the facility management team.
  • Site inspections shall be carried out at agreed stages, including before concealment of pipe works and during testing and commissioning.
  • Final acceptance shall be subject to satisfactory completion, testing, commissioning and submission of the required handover documents.

15. Bid Submission

Bids shall be submitted through the following email/address:info1@rwandatenni.rw 

The deadline for bid submission is set on 9/11/2026 at 12:00 PM.

The technical proposal and financial proposal shall be clearly presented. The financial proposal shall include a priced BOQ, applicable taxes and the total cost for the complete assignment.

16. Site Visit

Bidders are required to visit IPRC-Kicukiro before submitting their bids to inspect the six (6) tennis courts intended for irrigation. The visit shall enable bidders to assess site conditions, existing water storage arrangements, access, pipe installation routes and any other factors that may affect execution.

Bidders shall coordinate with Rwanda Tennis Federation (RTF) to arrange the visit and include proof of attendance with their bids. The site visit is scheduled from 26th/11/2026 to 2nd/12/2026 at RP -KIGALI COLLEGE TENNIS FACILITY.

17. Bid Evaluation Criteria

Bids shall first be checked for timely submission, completeness of required documents, eligibility and compliance with the mandatory requirements in these Terms of Reference. Bids that fail mandatory requirements may be rejected, subject to applicable procurement rules.

The evaluation shall be conducted in two stages:

Stage 1 – Technical evaluation (80 points):

  • Relevant company experience in the supply and installation of irrigation systems or comparable installations, supported by completion certificates or client references – 10 points.
  • Technical compliance and quality of the proposed irrigation equipment, including datasheets, specifications, suitability and conformity with the BOQ – 25 points.
  • Installation methodology and understanding of the assignment, including pipe routing, pump and control arrangements and site coordination – 20 points.
  • Implementation schedule, quality assurance, testing and commissioning plan, occupational health and safety and environmental management – 10 points.
  • Qualifications and relevant experience of the proposed key technical staff – 10 points.
  • Financial and logistical capacity, including ability to procure, deliver and mobilise the required materials and equipment – 5 points.

Bidders must achieve at least 70% of the available technical points (56 out of 80) to proceed to financial evaluation.

Stage 2 – Financial evaluation (20 points):

The financial proposal of each technically qualified bidder shall be evaluated for completeness, arithmetic accuracy, compliance with the BOQ and overall cost, including applicable taxes. The lowest evaluated responsive financial offer shall receive 20 points. Other offers shall receive proportionately fewer points using the formula:

Financial score = (lowest evaluated responsive price ÷ bidder’s evaluated price) × 20

Final ranking: The technical and financial scores shall be added to obtain a total score out of 100. The highest-ranked bidder whose bid is responsive and who meets the eligibility and qualification requirements shall be recommended for award, subject to applicable procurement rules.

Click on the APPLY button to send your application documents:
  • Your application will be sent to the employer immediately (Allowed formats: .doc .pdf .txt .docx)
  • A confirmation email will be sent to you few minutes afterwards
  • You can request any documents archived from our website (ex: a job description, a CV, a cover letter...)